Gantt Chart
Lili_Ana
✭
Hi,
I’d like my Gantt chart to show planned vs actual start and end dates. However, I don’t want to use the baselines option as I will be adding new deliverables/tasks as the project evolves and I don’t want to have to reset the baselines every time a new task is added. Is there a way to accomplish this?
Thank you,
Liliana
Answers
-
The only way to view two separate date sets on a single row in the Gantt view is to use the Baselining feature.
Come see me in Seattle at ENGAGE 2024! I will be at the 10xViz partner booth throughout as well as the "Lets Talk About Community" Meet & Eat table on Tuesday from 11:45am - 12:45pm!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63K Get Help
- 380 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 305 Events
- 34 Webinars
- 7.3K Forum Archives