Gantt Chart
Lili_Ana
✭
Hi,
I’d like my Gantt chart to show planned vs actual start and end dates. However, I don’t want to use the baselines option as I will be adding new deliverables/tasks as the project evolves and I don’t want to have to reset the baselines every time a new task is added. Is there a way to accomplish this?
Thank you,
Liliana
Answers
-
The only way to view two separate date sets on a single row in the Gantt view is to use the Baselining feature.