Baseline Visual in Gantt or Timeline view?
chlod24
✭✭
Hello! We have baselines set up on our sheet. Is there a way to show the variance visually, in the Gantt or new Timeline view - or is it only visible in that column as a number?
Thanks!
Tags:
Answers
-
It is visible in Gannt view when you select Show baselines in Gannt.
You will see a baseline under the Gannt bar. Toggle on and off to see the difference.