Hello,
The RM view of my project is stating that no one is assigned to my project, but, there are people assigned and the project plan shows that in the "Assigned To" column as well as the RM panel in the sheet. Why is the RM view saying no one is assigned?
Additionally, for one of the resources, Tuhin, there is a statement, "This user is not part of this Smartsheet Account". However, that user is a managed resource and it seems the assignment happened, at least in the sheet. What does the statement mean?
Here are screenshots illustrating the above question. The first shows the RM view stating no one is assigned, the second shown the project plan sheet with assignments. The third shows the statement about the user Tuhin and the fourth screenshot shows that the user in a managed user.