Calander view of durations
Is it possible to have multiple duataions transfered to calander view, form within one row.
I can add the columns but only the 1st set of dates works in transfering to the calander view.
We need this, as we have multiple visists to site for the same tast.
Is this issue the we currently have a Pro licence and need to upgrade?
Answers
-
That is standard across all levels. You can only display one set of dates in Gantt or calendar view on each row. You will need to create individual rows for each set of dates.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 146 Just for fun
- 63 Community Job Board
- 465 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!