Calander view of durations

AB_Tech
ββ
Is it possible to have multiple duataions transfered to calander view, form within one row.
I can add the columns but only the 1st set of dates works in transfering to the calander view.
We need this, as we have multiple visists to site for the same tast.
Is this issue the we currently have a Pro licence and need to upgrade?
Answers
-
That is standard across all levels. You can only display one set of dates in Gantt or calendar view on each row. You will need to create individual rows for each set of dates.