Project Plan at 99% complete, but all Tasks are 100% complete
I have a project plan set up with dependencies. All the parent rows have sub-tasks. When all sub-tasks are completed at 100%, the Parent for the overall project still reads 99%
Best Answer
-
@Ray Lindstrom Thanks for the tip on the duration. I found a ghost row at the bottom that was a child row of the overall project, but did not have anything populated but a 1d duration. Removing that fixed it.
Answers
-
My guess would be that you have a blank duration on one of your rows.
-
@Ray Lindstrom There was one for an item that the date gets added mid project. But I added 1 day and a date and still not fixed
-
@Ray Lindstrom Thanks for the tip on the duration. I found a ghost row at the bottom that was a child row of the overall project, but did not have anything populated but a 1d duration. Removing that fixed it.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!