Project Plan at 99% complete, but all Tasks are 100% complete
I have a project plan set up with dependencies. All the parent rows have sub-tasks. When all sub-tasks are completed at 100%, the Parent for the overall project still reads 99%
Best Answer
-
@Ray Lindstrom Thanks for the tip on the duration. I found a ghost row at the bottom that was a child row of the overall project, but did not have anything populated but a 1d duration. Removing that fixed it.
Answers
-
My guess would be that you have a blank duration on one of your rows.
-
@Ray Lindstrom There was one for an item that the date gets added mid project. But I added 1 day and a date and still not fixed
-
@Ray Lindstrom Thanks for the tip on the duration. I found a ghost row at the bottom that was a child row of the overall project, but did not have anything populated but a 1d duration. Removing that fixed it.
Help Article Resources
Categories
Check out the Formula Handbook template!