How to split task time if you have a on hold time in the middle of it?
I have a task that will have to be on hold for a month and then restart? I know MS Project has this break in the middle and you can break the progress bar into 2 sections. Is there a way to do it here in SS?
Answers
-
You can create a task called 'on-hold' and add lag time, making the actual task the dependent and hence it will begin when that finishes.
Or you can add lag time to an already existing predecessor (e.g. FS+12D).
See more here in the help article:
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.8K Get Help
- 406 Global Discussions
- 218 Industry Talk
- 457 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 297 Events
- 37 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!