I'm afraid I know the answer to this, but I'm working with a very large project plan and I want to flag one task in a report (or maybe a filter? or… a helper sheet?) where I can isolate that one critical task and all if its predecessors.
The goal is to see in one view that task and every other task that precedes it (or has that task as a successor).
Reports by default do not carry over predecessor data. They only show that a predecessor exists. The screenshot below is a snippet of a report.
Let me know what you think. I'm wondering if the helper page may work, with conditional lookup or index / match function.
Thanks!
P.S. If you interested in the TOTALFLOAT field, the purpose of this ask is to use the TOTALFLOAT to ID opportunities to accelerate predecessor tasks so that the Successor (the "one critical task") can be completed sooner.
That's why I'm trying to think of a way to isolate the floats of predecessors to impact the successor.