Hello - I am managing a Smartsheet action item log. I need any row that is deemed 'complete' to be moved down into a completed section further down the sheet. Is there a way to set this up to be automatic vs. manual?
There is currently no Smartsheet solution for doing what you suggested. There are third-party apps that will perform some of this functionality. This post suggests 3 options: https://community.smartsheet.com/discussion/automatic-move
None of them are perfect. However, there is a solution that could allow you to move rows with a simple sort.