Hi @A. Rivera,
There's no way to not use a child row towards the parent's % Complete. You can however use automation to update the % Complete to 100 for the Not Applicable rows to save yourself the administrative burden.
-
Thank you for the advice. In order to utilized automation, will I have to remove the dependencies? What kind of automation will work best? I apologize if I'm asking too many questions, I just started utilizing smartsheet a month ago.
-
-
Thank you, Ray! It worked!
-
No problem, happy to help! 😊
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.9K Get Help
- 379 Global Discussions
- 212 Industry Talk
- 442 Announcements
- 4.6K Ideas & Feature Requests
- 140 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 302 Events
- 33 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!