Formula Help: Risk Flag based on End Date

itSmE
✭✭
Can someone help me create a formula based on end date
If EndDate is <TODAY and Status Does Not Equal "completed" Red Flag in Risk Column
TIA
Best Answers
-
Formula:
=IF(AND([End Date]@row < TODAY(), Status@row <> "Completed"), 1, 0)
Leroy Noriega | Smartsheet SME | Independent Smartsheet Consultant
Core App, Project Management and System Administrator Certified🏅
E: leroy.noriega@yahoo.com | Linkedin Profile
-
Perfect - thanks Leroy
Answers
-
Formula:
=IF(AND([End Date]@row < TODAY(), Status@row <> "Completed"), 1, 0)
Leroy Noriega | Smartsheet SME | Independent Smartsheet Consultant
Core App, Project Management and System Administrator Certified🏅
E: leroy.noriega@yahoo.com | Linkedin Profile
-
Perfect - thanks Leroy