Predecessor business days

I need to calculate a projected timeline based on a predecessor, but only in business days. How do I do that?

Answers

  • Matt Lynn-PCG
    Matt Lynn-PCG ✭✭✭✭✭✭

    @kborrell

    Go to the gantt settings and select the days you want it to calculate with.

    Certified Platinum Partner

    2023 Partner of the Year

    PrimeConsulting.com

  • Sorry, I wasn't clear. Not all of my dependencies will be based on business days. What I'm trying to do is take a task…say line 508. Referring back to that line saying 508+4 (business days). Is that possible?

  • AravindGP
    AravindGP ✭✭✭✭✭✭

    Hi @kborrell

    While you can set lag days, you can't define for it to be business days if you haven't set it up in Working Days as shown by Matt. It will just be 508+4d (which will be 4 days). You are left to manually check if the 4th day is a business day or not.

    Thanks,

    Aravind GP| Principal Consultant

    Atturra Data & Integration

    M: +61493337445

    E:Aravind.GP@atturra.com

    W: www.atturra.com