Predecessor business days
I need to calculate a projected timeline based on a predecessor, but only in business days. How do I do that?
Answers
-
Go to the gantt settings and select the days you want it to calculate with.
Certified Platinum Partner
-
Sorry, I wasn't clear. Not all of my dependencies will be based on business days. What I'm trying to do is take a task…say line 508. Referring back to that line saying 508+4 (business days). Is that possible?
-
Hi @kborrell
While you can set lag days, you can't define for it to be business days if you haven't set it up in Working Days as shown by Matt. It will just be 508+4d (which will be 4 days). You are left to manually check if the 4th day is a business day or not.
Thanks,
Aravind GP| Principal Consultant
Atturra Data & Integration
M: +61493337445
E:Aravind.GP@atturra.com
W: www.atturra.com
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.6K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 63 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives