Remaining Working Days Calculation
Howdy,
I have been looking at various community posts, and I am still unable to find an answer.
COLUMN D is DUE DATE
COLUMN E is WORKING DAYS REMAINING
Row 1, Column D date is 9/29/24. What is the formula I can use in Row 1, Column E that I can copy down the rest of the sheet?
Best Answers
-
=NETWORKDAYS(TODAY(),[DUE DATE]@row)
That should work. Right click the cell and make it a column formula to fill down.
-
That worked perfect! Thanks!
Answers
-
=NETWORKDAYS(TODAY(),[DUE DATE]@row)
That should work. Right click the cell and make it a column formula to fill down.
-
That worked perfect! Thanks!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives