Hi there,
I am trying to do a formula that says something along the lines of the below:
- If all tasks are marked as complete, update parent to Complete
- If any task is marked as 'in progress' update parent to In Progress
- If no tasks are started, update parent to Not Started
- If majority of tasks are marked as Potential Risk OR Risk / Delay update parent to At Risk
- If all tasks are NA / canceled, update parent to Canceled
My status options are:
|
| Not Started | |
|---|
|
| In Progress | |
|
| Potential Risk | |
|
| Risk / Delay | |
|
| Complete | |
|
| NA /Canceled | |
I tried looking at other community posts, and found this, but I'm not sure how to incorporate my additional statuses.
=IF(COUNTIFS(CHILDREN(), "In Progress") > 0, "In Progress", IF(COUNTIFS(CHILDREN(), "Not Started") > 0, "Not Started", "Complete"))
Please can someone advise? Appreciate any help!
Thanks!
Rosie