Formula issue

Hi Brian Trust
My formula wont work
LOGIC
- If the Helper Date Column is blank then the priority cell is blank
- If the Helper Date Column is less than 10 days, its Low Priority
- If the Helper Date Column is greater than 10 days, its High Priority?
FORMULA
=IF(ISBLANK([DD 10 Day - Helper Column]@row), "", IF(NETWORKDAYS(TODAY(), [DD 10 Day - Helper Column]@row) <= 10, "Low", "High"))
- f the Helper Date Column is blank then the priority cell is blank - WORKS
- If the Helper Date Column is less than 10 days, its Low Priority - WORKS
- If the Helper Date Column is greater than 10 days, its High Priority? - WONT WORK
What have I done wrong?
Answers
-
@Susan van Niekerk its a pleaseure to meet you , great to see your engagement!
Try this instead:
working days
=IF(ISBLANK([DD 10 Day - Helper Column]@row), "", IF(NETWORKDAYS(TODAY(), [DD 10 Day - Helper Column]@row) <= 10, "Low", "High"))
Calendar Days
=IF(ISBLANK([DD 10 Day - Helper Column]@row), "", IF([DD 10 Day - Helper Column]@row - TODAY() <= 10, "Low", "High"))
If my comment helps you, I appreciate a 💡
Kind regards
Nico | LinkedIn
CEO | Lighthouse Consultings
Lecturer in Business Information Systems | DHBW
________________________________________________________________________________
addvalue@lighthouseconsultings.com
We offer Licenses - Training - Solution Engineering
🔴 GOLD Smartsheet Partner _______________________________________________
💯 SCALEABLE Solutions Engineered by Lighthouse Consultings
We Don’t Just Implement Smartsheet; We Revolutionize How You Manage, Plan, And Execute.
Help Article Resources
Categories
Check out the Formula Handbook template!