My parent rows are not rolling up start/end dates and "Status"?
I have some parent rows where rollups are working (duration, start date, end date and % completion, status), while other parent rows only show duration and % completion- missing "rolled up" start and end dates and "status".
Under "edit project settings", I have dependencies enabled (I checked for "duration", "start date", "end date", and "% completion" and "status"
columns). Why are some parent rows working while others are not?
Answers
-
Those are the only columns that roll up by the system.
If you want to roll up another column, status, for example, you must write a formula.
In the following discussion, the formula guru @Paul Newcome gives an excellent formula.
-
For Status rollup, I use 2 easy automation workflows. One sets the status to In Process, the other to Complete. This one sets the status to In Process.
This one is for Completes:
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.1K Get Help
- 450 Global Discussions
- 155 Industry Talk
- 505 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 80 Community Job Board
- 514 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives