I am trying to create a task sheet with several projects on each row with phases

I am looking to have over 50 projects in one sheet and track the various high level stages of each project by assigning to the next resource. Can I put the stages as a drop down coulumn and as each team member finishes their stage they can assign to the next resource? What would be a good template to use? I am very new at smartsheet…. just a beginner.

Best Answer

  • mcarlson
    mcarlson ✭✭✭
    Answer ✓

    Hi!

    Yes, using a dropdown column to track stages and assigning the next resource in each stage can be an effective approach in Smartsheet for managing multiple projects in a single sheet. Here’s how you can set it up:

    1. Create a Dropdown Column for Stages: Set up a column with a dropdown list for each stage of your project workflow. This way, each team member can update the status as they complete their stage.
    2. Assign Resources: Add an “Assigned To” column with a contact list. This allows team members to assign the next resource directly from Smartsheet once their part of the workflow is complete.
    3. Automation Rules: Consider setting up automated workflows to notify or alert the next resource when the stage changes. For example, you can create a rule that triggers an alert or assigns the task when a new stage is selected.

    For templates:

    • Project Tracking and Rollup: This template lets you track multiple projects in one sheet and is great for high-level visibility.
    • Project Pipeline Template: This is useful if you’re managing multiple projects with specific stages or phases and need to see where each project stands in a pipeline format.

    Using these templates as a base, you can customize them with dropdown columns for stages and assign resources as each project moves forward.

    Please feel free to email me for further assistance!

    Murphy Carlson

    DigitalRadius, Smartsheet Platinum Partner

    Schedule a Meeting

    mcarlson@digitalradius.com

Answers

  • mcarlson
    mcarlson ✭✭✭
    Answer ✓

    Hi!

    Yes, using a dropdown column to track stages and assigning the next resource in each stage can be an effective approach in Smartsheet for managing multiple projects in a single sheet. Here’s how you can set it up:

    1. Create a Dropdown Column for Stages: Set up a column with a dropdown list for each stage of your project workflow. This way, each team member can update the status as they complete their stage.
    2. Assign Resources: Add an “Assigned To” column with a contact list. This allows team members to assign the next resource directly from Smartsheet once their part of the workflow is complete.
    3. Automation Rules: Consider setting up automated workflows to notify or alert the next resource when the stage changes. For example, you can create a rule that triggers an alert or assigns the task when a new stage is selected.

    For templates:

    • Project Tracking and Rollup: This template lets you track multiple projects in one sheet and is great for high-level visibility.
    • Project Pipeline Template: This is useful if you’re managing multiple projects with specific stages or phases and need to see where each project stands in a pipeline format.

    Using these templates as a base, you can customize them with dropdown columns for stages and assign resources as each project moves forward.

    Please feel free to email me for further assistance!