Elapsed Duration with 'e' Adding an Extra Day and Ignoring FS Predecessor
System
Employee
This discussion was created from comments split from: Elapsed duration is calculating one additional day.
Answers
-
Same here - I have a 5-day week set in gantt, but use "e" to capture the weekend, since only a few tasks need to include weekends. But the predecessor is ignoring the FS, essentially adding a day to the duration.
so if my predecessor ends today, the next task with e2 includes today instead of starting tomorrow. See below clip:
-
Unless you have it set up differently, when you use an "e" it starts on the same day as the finish in the predecessor, but those without the "e" start the following day. You can read more about it here:
Michelle Choate
michelle.choate@outlook.com
Always happy to walk through any project you need help with!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.5K Get Help
- 424 Global Discussions
- 136 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 145 Just for fun
- 62 Community Job Board
- 464 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 301 Events
- 39 Webinars
- 7.3K Forum Archives