Budget Rollup based on used Resources

I currently have this formula for my budget
=IF([Resource Helper column]@row > 4, [Quoted labor budget ]@row - (200 * ([Resource Helper column]@row - 4)), [Quoted labor budget ]@row).
I want to do a roll up each time an additional resource is added in the child rows and any additional rows for created for each project.
Im currently using 1 sheet for all of my projects
Answers
-
Can you explain more of what you are looking for? Would it be easier to jump on a quick zoom to look at your sheet and create a quick formula? If so - my calendar is linked below. Happy to chat with ya!
Michelle Choate
michelle.choate@outlook.com
Always happy to walk through any project you need help with! Book time with me here: https://calendly.com/michelle-choate
-
To create a roll up of all children rows (excluding any additional IF criteria) you can simply use a =sum(children()) on each parent row, so when a new child row (project) is created, the sum value will automatically update