Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Resource Allocation in Parent Rows
Does Smartsheet allow resource loading parent rows? I am trying to assign parent rows to staff and allocate percentage on the parent row, but it does not allow allocation entry on the parent row. I do have resources enabled on the sheet. I do not want the parent row to sum the allocation percentage of the child rows.
Thanks.
Comments
-
Hello,
There currently isn't a way to manually assign resource % on parent row when resource management is enabled. Resource Management will always roll up allocation % to the parent.
When you have a moment, submit a Product Enhancement Request using the form under Quick links on the right and let our Product team know your use case for resource loading in the parent.
-
Will do. Thank you.
-
Is there any way to get the Allocation % to Roll-up to the parent row?
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives