Hi Community!
I'm having a problem with automations. I added new automations to my template that was originally used to create some existing projects.
Once I added the automations to the template, existing projects immediately inherited the new automations and now they're ALL broken. See screenshots. When I tried to start over and delete all the workflows in the old project, Smartsheet started to delete working automations in the template. How are they linked and is it possible to unlink them? The existing projects are already populated with data that will be very labor intensive to replace.
Thanks for the help!
Aja