Recurring Meetings in Schedule

Hi,

I am developing a project schedule and wish to include bi-weekly client meetings. Is there a way that a task can be shown as recurring on a schedule? Ideally this would show in a single row.

Thanks

Answers

  • Community Champion

    There are different ways to accomplish recurring meetings. Can you provide a screenshot of your project schedule columns, and how you envision it working? Because there might be a way to use a helper column to record a date, and a formula to have that date be two weeks past the last recorded date.

    Michelle Choate

    michelle.choate@outlook.com

    Always happy to walk through any project you need help with! Book time with me here: https://calendly.com/michelle-choate