Gantt

I'm running multiple projects and reporting all in one consolidated Report / Dashboard with Gantt timelines.
I'm trying to show one project on one Gantt line, however, break up the bar into different colors for each of the phases within the project. Is this possible, and if yes, how would I set it up?
Answers
-
This is not currently possible. Take a look through the Product Ideas tab at the top of this page to see if the idea has already been submitted. If it has, you can add your vote. If it has not, you can submit the idea yourself to allow others to vote on it. Either way, please feel free to provide a link to the idea here on this thread so that others searching for somethign similar are able to easily add their votes.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.1K Get Help
- 450 Global Discussions
- 155 Industry Talk
- 505 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 80 Community Job Board
- 514 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives