Predecessor doesn't always update Start Date for some rows.
Hi all,
I'm hoping to get some community help/direction with this please.
I've been using the same PMO project plan template for over a year now. Recently, I find when I modify the predecessor (+ or - days), the Start Date doesn't change. This doesn't happen for all rows but is consistent with the rows where it happens. I'm modifying children rows only.
Specifically, rows 84 and 85. It doesn't matter what change is made to the lag time, the start date doesn't change.
Answers
-
hi @Kathy PPT
can you show me how it looks on your gantt chart?
I just tested and for me it looks pretty ok:
Experienced IT PM and the Real Smartsheet Enthusiast.
Is there anything else we can help you with? - book your time.
MASA Consult - Your Aligned Smartsheet Gold Partner
Find us on LinkedIn & Check our Smartsheet Solutions!
Tag my name: @kowal if you want me to respond :)
-
@kowal, I marked the two rows in question.
-
hi @Kathy PPT,
thanks for the screenshot yeah for me looks like a bug because if you create a lag the arrow shall go back as on my screenshot.
actually i never had such issue with my projects so I would wait for someone here who might have had such problem or you can go directly to Support.
Experienced IT PM and the Real Smartsheet Enthusiast.
Is there anything else we can help you with? - book your time.
MASA Consult - Your Aligned Smartsheet Gold Partner
Find us on LinkedIn & Check our Smartsheet Solutions!
Tag my name: @kowal if you want me to respond :)
-
@kowal, thank you!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.1K Get Help
- 450 Global Discussions
- 155 Industry Talk
- 505 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 80 Community Job Board
- 514 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives