Milestones in Baseline in Reports

Hi,
I have Miletsone in my project plan which appears as diamond in Gantt chart and there is one more diamond for Baselines in Gantt chart. But when I make Report out of it, there is just one diamond in Gantt instead of two. Please find below screenshots and please help on how to have 2 diamonds in Reports similar to sheets for duration.
Answers
-
hi @Kamya Pamnani,
it could be that in the sheet you have the actual dates and planned dates that's why you see two milestones (diamonds) however in the report you can only see the milestone for the real dates.
Experienced IT PM and the Real Smartsheet Enthusiast.
Is there anything else we can help you with? - book your time.
MASA Consult - Your Aligned Smartsheet Gold Partner
Find us on LinkedIn & Check our Smartsheet Solutions!
Tag my name: @kowal if you want me to respond :)
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.1K Get Help
- 450 Global Discussions
- 155 Industry Talk
- 505 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 80 Community Job Board
- 514 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives