Gantt scheduling

MRR
MRR
edited 06/05/25 in Smartsheet Basics

we’re in construction and developing a working schedule. What’s the best way to easily insert a rain day to a task for instance that alters finish date without changing the duration amount.

Answers

  • kowal
    kowal Overachievers Alumni

    hi @MRR ,

    Unfortunately it's not possible as for now to make a break in the task aka rainy day. If you have the Start Date and End Date the duration will be always automatically calculated between those.

    You can build a workaround like adding extra column where you can add the "days" that did not work and have 2nd duration for your needs but Gantt schedulling will not show it.

    Tomasz Kowalski

    Experienced IT PM and the Real Smartsheet Enthusiast.

    Is there anything else we can help you with? - book your time.

    MASA Consult - Your Aligned Smartsheet Gold Partner

    Find us on LinkedIn & Check our Smartsheet Solutions!

    Tag my name: @kowal if you want me to respond :)