Gantt scheduling

we’re in construction and developing a working schedule. What’s the best way to easily insert a rain day to a task for instance that alters finish date without changing the duration amount.
Answers
-
hi @MRR ,
Unfortunately it's not possible as for now to make a break in the task aka rainy day. If you have the Start Date and End Date the duration will be always automatically calculated between those.
You can build a workaround like adding extra column where you can add the "days" that did not work and have 2nd duration for your needs but Gantt schedulling will not show it.