How can I add a new task that's start date is in the past?

TheoAyesWay
β
Hey community
I need to add a task into a project plan that has it's start date in the past. Seems like the system does not allow that?
Tags:
Answers
-
hi @TheoAyesWay,
Of course you can add the start date of any task in the past but:
- is this stand alone task or are the dates pending on some predecessors
- is this a main task or subtask of other task where the start and end date are define.
Experienced IT PM and the Real Smartsheet Enthusiast.