How can I add a new task that's start date is in the past?
Answers
-
hi @TheoAyesWay,
Of course you can add the start date of any task in the past but:
- is this stand alone task or are the dates pending on some predecessors
- is this a main task or subtask of other task where the start and end date are define.
Experienced IT PM and the Real Smartsheet Enthusiast.
Is there anything else we can help you with? - book your time.
MASA Consult - Your Aligned Smartsheet Gold Partner
Find us on LinkedIn & Check our Smartsheet Solutions!
Tag my name: @kowal if you want me to respond :)