Task Durations
Hi All,
I have created a project plan using a Smartsheet template. I have multiple tasks and resources, each with different allocations.
However, I am encountering an issue with calculating task duration. Since my resources have varying allocations, I would expect, for example, that if a resource is allocated at 50% and the task effort is 8 hours, the duration should be 2 days. However, in Smartsheet, every task duration defaults to 1 day.
In MS project, task duration is automatically calculated based on resource allocations.
Is there a specific calculation I should be using in Smartsheet, or am I missing something?
Answers
-
hi @LeanneG87,
Yeah In smartsheet if 8h it means the duration is 1 day.
If you allocate your resource by 50% it will be 4h which is one day.
Experienced IT PM and the Real Smartsheet Enthusiast.
Is there anything else we can help you with? - book your time.
MASA Consult - Your Aligned Smartsheet Gold Partner
Find us on LinkedIn & Check our Smartsheet Solutions!
Tag my name: @kowal if you want me to respond :)