Timeline not showing correctly

Options
Paul69g
Paul69g
edited 07/02/25 in Smartsheet Basics

Hi All

I have generated a live savings tracker, with savings being driven by live project plan end dates.

I have created a gantt with a single line for each project and I am pulling the live end date for each project from the BPS using an index match formula. I then use a short formula to add 365d to the the live end date give savings date.

This all works fine for getting the dates in, however the timeline view only displays as a milestone and doesn't show all the info selected. The only way to display the timeline correctly as a bar with all required info is to enable dependencies which works great, however the formula to grab the live end date for the BPS then disappears and i am left with a static date….no longer a live tracker!

Any help would be gratefully received

Paul