I would appreciate some guidance on a common project scheduling practice in Smartsheet.
Typically, resource allocation (% allocation) and assigned resources are defined before building the WBS. Task start and end dates should then be driven by both task duration and the assigned resource’s availability.
For example, if Task A has a 2-day duration and is assigned to Peter, who is only allocated 50% to the project, the task should effectively take 4 days to complete. However, after configuring Assigned Resource, % Allocation, and Duration in Smartsheet, the task still shows a 2-day duration and does not adjust based on allocation.
Is there a way to configure Smartsheet to reflect this behavior, or is this not supported?