Hello,
The majority of the time we import an MS Project schedule and have had no problems with pulling those into a report. However, if we create a new blank Project Sheet and enter the tasks through the web interface, those sheets do no get pulled into the report.
The columns for the Start & End dates are different between the two, but even if we manually change them to be the same either through inserting them or renaming them, the "native" Project Sheet does not get pulled in.
I tried modifying the report to test against the two different columns for start and end dates, but that also did not correct the problem.
Any suggestion as to what else to try?
Regards,
Ron