Hi,
I am currently trying out Smartsheet in order to decide if we will be able to use this at our company or not.
I'm using the construction timeline with gant chart template.
I would like to add project management fee payment dates as milestones.
Payment #1 linked to start of the project -> OK, no problem
Payment #3 linked to end of the project -> OK, no problem
Payment #2:
I'd like to use the formula Start date of payment 1] + ([Start date of payment 3] - [Start date of payement 1]) / 2
It looks like it is not possible however to use a formula in the [Start Date] column if dependencies are enabled for the sheet. If dependencies are disabled I can use a formula, but then the milestone feature is not available.
Apart from calculating the date manually and update everytime the project start / end date changes, is there another way to do this?