% Complete not reflected on parent task
I have a task with subordinate tasks, the highest level is not calculating with the rest of the sheet. I have precisely the same setup throughout the sheet and the rest work. Any ideas?
Comments
-
Hello,
Thanks for this question! Could I have you check that dependencies are enabled on the sheet? I would assume so because your other "% Complete"s roll up, but I just wanted to verify.
Secondly, could I have you provide a full-sheet screenshot of what you're seeing on the sheet? If needed, you can black out sensitive information such as email addresses.
Kind regards,
Alison
Smartsheet Support -
I have the same issue where parent lines do not calculate child percent complete into the summary parent line. I've tried using both dependency enabled and disabled.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives