Sign in to join the conversation:
I have a task with subordinate tasks, the highest level is not calculating with the rest of the sheet. I have precisely the same setup throughout the sheet and the rest work. Any ideas?
Hello,
Thanks for this question! Could I have you check that dependencies are enabled on the sheet? I would assume so because your other "% Complete"s roll up, but I just wanted to verify.
Secondly, could I have you provide a full-sheet screenshot of what you're seeing on the sheet? If needed, you can black out sensitive information such as email addresses.
Kind regards,
AlisonSmartsheet Support
I have the same issue where parent lines do not calculate child percent complete into the summary parent line. I've tried using both dependency enabled and disabled.
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…