Hi All
i am very new to SmartSheet. I am working on the project template which can help to highlight some tasks that have been overdue with RYG. Need your kindly help on the formula...
1. If task status is complete: Green
2. If the task status is Not Started: 1. Scheduled End Date is behind today: Grey. 2. Scheduled End Date is before Today: Red
3. If the task status is Pending: 1. Scheduled End Date is behind today: Yellow. 2. Scheduled End Date is before Today: Red
4. If the task status is In Progress: 1. Scheduled End Date is behind today: Green. 2. Scheduled End Date is before Today: Red
And also for the parent task: if any subtask status is Red, it will be red. Or if any subtask status is Yellow, it will be yellow, otherwise it will be green.
Really appreciate for any comments, thanks in advance.