Please see attached screenshot
In a separate field (that I haven’t yet created), I would want to know the % availability (based on 40hr work week) of each assigned resource based on each active request status.
Hi Darcie,
You might need to test this out a bit more extensively, but I was able to come up with a formula for resource allocation based on your sheet:
=SUMIFS([Est Hours]:[Est Hours], [Assigned To]:[Assigned To], "Person A", [Request Status]:[Request Status], OR(@cell = "In Process", @cell = "Approved By Mgr")) / 40
This summarizes all of the estimated hours of projects that have been approved and are assigned to "Person A." It then divides them by 40 to give you their percent allocation.
A few notes on this:
Let me know if you have any questions.
Date Report Partner CBO Name 01/12/25 Children's org 05/15/25 Foodbank 08/30/25 Children's org 09/11/25 Chamber 11/25/25 Digital Bus 08/21/24 Digital Bus South 01/15/26 Children's org 01/12/24 Foodbank Sister 02/15/24 For the children org 07/01/26 Digital Bus #2 08/05/26 Family Center 12/01/26 Family Center I am trying to…
I am trying to get the passenger count per month per year, and I can't seem to get the formula correct. I need to add the number of passengers for each month per year. If anyone could assist me with this, I would greatly appreciate it. Thanks!
I need to edit a large sheet that has a lot of predecessors. I need to delete one row and move another. when I make the changes the predecessors for proceeding lines are not correctly displaying the dates correctly. Need help.