Report Builder - Not Sorting Dates
Hello -
I running reports for partners on the team to provide the user a snapshot of tasks due earliest date to latest date. When I sort A to Z on the finish date it is not working. Any ideas
Comments
-
Hello,
A couple of questions to guide your troubleshooting:
- Does the issue occur on other reports?
- Does the issue persist if you build a new report with the same criteria?
- Are you sorting from the column header drop down or from within the Report Builder?
Thanks,
Schiff
Smartsheet Support -
Hi Schiff-
Yes the issue occurs on other reports. I basically have the criteria the same for all reports except I build out the reports across the team changing the "Assigned To" field. I am soring from the column header drop down.
Thanks-
Jim
-
Hi Jim,
At this stage I recommended opening a support ticket for this issue here: https://help.smartsheet.com/contact
The support team has some back end tools which often resolve these types of issues.
When submitting your request, be sure to give the Smartsheet login email address of the owner of any affected reports.
Thanks,
Schiff
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 143 Just for fun
- 58 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives