I want to create a formula in a cell that subtracts a certain number of days from another cell that is linked to another persons Smartsheet. How would I do that? My efforts have failed.
Hi there,
This is pretty simple. After you have linked the cell... you can use simple math to adjust the days. For instance. If you have a linked cell in [Column2] row 3 and want to add 10 days to it. In a new column (set up as a date column) and row, use the following formula. Do note that because you are creating a new date you need to use the Date Column type to make that happen.
=[Column2]3 + 10
If you want it to be 10 days before that date use this formula
=[Column2]3 - 10
If you want it to be 10 working days after the linked cell date and you have set up your working days in your account settings.
=Workday([Column2]3,10)
Or 10 days before.
=Workday([Column2]3,-10)
Hope that helps!
I have a parent row that I'm using to sum all child row values where Children = 0 and Status = "Not Started". This is my formula. =IF(OR(ISBLANK(Status@row ), Hierarchy@row = 0), "", IF(Hierarchy@row = 1, SUM(CHILDREN()), IF(AND(Children@row = 0, Status@row = "Not Started"), 1, 0))) However, if any of my task rows are…
Hi, I am trying to get a column that provides the Date (easy with Record a Date) but I need the TIME as well. Most of my tables I just use the right function on the Modified Date because the only thing updating those tables are automations or data imports. But a few tables have automations, data imports, and manual inputs.…
I’m hoping to get a second set of eyes from the community in case I’m missing something obvious or there’s a cleaner pattern I should be using. I’ve used ChatGPT to try and help me group/organize my situation coherently…. Because at this point I feel crazy… I’ve literally worked on this for hours. Environment •Smartsheet…