Hello Community,
I would like to nest a short checklist of rows under an activity in a Project Sheet such that the nested rows representing the checklist do not require durations and dependencies.
However, SmartSheet requires the duration and dependency on each nested row, where I repeat the same data, so it rolls up to the header row consistently.
Any tips or tricks to maintain duration and dependencies just on the header row, and not any rows nested under? Or is that just the way a Project Sheet has to work for the overall Gantt to work.
Would be nice if there was a way to set the nested rows as 'for info only' and maintain the duration and dependency on the header row to drive the Gantt.
Thank you.