Is there any way to have collaborators being able to open gantt charts at today's date instead of the earliest date?
Hi Doug,
There is a setting that you can change in the Project Settings. Please see attached link/screenshot.
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant / Get Done
Hi Andrée
thank you. Yes I have this turned on, but this setting is not available for collaborators and the setting only works for my log in.
Any other suggestions are very welcome.
thanks
Doug
Hi again Doug,
I just checked and yes that's correct. I'll come back to you if i discover someway to workaround it.
Please submit an Enhancement Request when you have a moment.
I've created a Smartsheets form. When someone submits the form, I want them to automatically be emailed a document that has resources and links, but the document is filtered to only show the content that corresponds with what they selected in the form. Is something like this possible? What types of documents or automations…
I have a sheet that I created in a previous version, and it had a form. I was recently upgraded to a newer version and now my form is not working. I created a new form for the sheet, and it is giving me an error also. Does anyone know what I can do to fix this? The error says Form Unavailable. Sorry, the form you're trying…
Hi, I have read the post from 8/21/25. I am still getting the same error. I am setting up a new device and just download the latest version as of 9/5/25. I am using a Eunivon Smart White Board for touchscreen capability. It is running Android 14. Any help would be appreciated.