Dependencies - with time between items
This is the senario:
Line 1:
Start date January 1st.
Duration 5 days
Line 2:
Start date January 15th.
Duration 5 days.
I want the two lines to be dependent so that line 2 can't start before line 1 is done.
However, Line 2 should not start before the 15th.
My problem is that if I create a dependency, the startdate of line 2 will automatically change to January 6th.
Comments
-
Try a Start to start dependency with a 10 ed lag
-
But I don't want the lag to be fixed to i.e. 10 days.
Even if the first event is delayed, it is not a problem until we pass the start date of event 2.
Example.
Line 1: Prepare Powerpoint for a meeting
Line 2: Meeting at a fixed date. (People invited).
A delay in Line 1 is not a problem, until the end date will pass the start date of Line 2.
-
You need a second dependency. Make a milestone on 10th January and make Line 2 a successor to the milestone as well as line 1.
When the milestone date passes, Line 2 can start. If Line 1 is delayed and doesn't end until after 10th January, it will become the driver of line 2.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 140 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives