Can I zoom out on the resource view to show the timeline by month and quarter and not just week, which is the default?
Hello,
At this time the resource view only shows resource allocation by week/day. You can let our product team know that you'd like resource views by month/quarter by clicking on the Submit Product Enhancement Request link on the right-side pane of Community pages
Thanks!
Schiff
Smartsheet Support
Has there been any progress on this issue? I assume someone logged an Enhancement Request back in 2018?
The export function provides a rather clunky table that limits the ability to analyze Resources any more than a day-by-day assessment. Per the OP, having a Weekly/Monthly report would be very handy, particularly for projects running longer than 12 months.
Anything on the Roadmap @Genevieve P ?
Regards,
Richard.
Hi @Richard Heath
No, there haven't been any recent updates to the Resource Report View in Smartsheet; the Report still shows resource views from a weekly perspective. You may want to look into 10,000ft (see here) to display different resource views for projects that span over 12 months.
Cheers,
Genevieve
@Paul Newcome , Hope you are well. Question for you, meant to ask quite some time ago but forgot. You had shared this right after Engage 2025. I'm unfamiliar with the view and how to create it. Can you tell me about this view?
I am trying to change owner on a Smartsheet sheet to the owner of the workspace it is located in. I keep getting an error message stating the permissions need to be managed at the workspace level. I am unable to change owner for the sheet at the workspace level. Not sure how to accomplish this change. HELP!
I would like to add two dynamic filters as a widget within my Dashboard to define a date range (start and end date) which would then return a count value to that same Dashboard. I have been searching for answers but am not coming up with the solution I'm looking for. What is the cleanest way to configure this?