Can I zoom out on the resource view to show the timeline by month and quarter and not just week, which is the default?

Comments

  • Schiff A.Schiff A. Employee

    Hello,

     

    At this time the resource view only shows resource allocation by week/day.  You can let our product team know that you'd like resource views by month/quarter by clicking on the Submit Product Enhancement Request link on the right-side pane of Community pages

    Thanks!

    Schiff

    Smartsheet Support

  • Richard HeathRichard Heath ✭✭✭✭

    Hello,

    Has there been any progress on this issue? I assume someone logged an Enhancement Request back in 2018?

    The export function provides a rather clunky table that limits the ability to analyze Resources any more than a day-by-day assessment. Per the OP, having a Weekly/Monthly report would be very handy, particularly for projects running longer than 12 months.

    Anything on the Roadmap @Genevieve P ?

    Regards,

    Richard.

  • Hi @Richard Heath

    No, there haven't been any recent updates to the Resource Report View in Smartsheet; the Report still shows resource views from a weekly perspective. You may want to look into 10,000ft (see here) to display different resource views for projects that span over 12 months.

    Cheers,

    Genevieve