Critical path disappeared

JohnD256
✭✭
I was updating a project gantt chart and at some point the critical path red outline disappeared (no I didn't turn it off, I checked!)
What is required that this is visible? I had to break some task dependencies to get the bars to actually show real-world dates, could that be it?
Tags:
Comments
-
Hello,
Critical path is calculated based on dependencies starting from the task with no predecessors, at least one dependency, and the latest end date.
If you've broken dependencies from your task with the latest end date, then you may have stopped your critical path. More info on critical path is available here: https://help.smartsheet.com/articles/1979152-tracking-a-project-s-critical-path
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.3K Get Help
- 462 Global Discussions
- 156 Industry Talk
- 508 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 517 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 308 Events
- 36 Webinars
- 7.3K Forum Archives