Critical path disappeared
JohnD256
✭
I was updating a project gantt chart and at some point the critical path red outline disappeared (no I didn't turn it off, I checked!)
What is required that this is visible? I had to break some task dependencies to get the bars to actually show real-world dates, could that be it?
Tags:
Comments
-
Hello,
Critical path is calculated based on dependencies starting from the task with no predecessors, at least one dependency, and the latest end date.
If you've broken dependencies from your task with the latest end date, then you may have stopped your critical path. More info on critical path is available here: https://help.smartsheet.com/articles/1979152-tracking-a-project-s-critical-path
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.4K Get Help
- 394 Global Discussions
- 213 Industry Talk
- 449 Announcements
- 4.6K Ideas & Feature Requests
- 141 Brandfolder
- 132 Just for fun
- 131 Community Job Board
- 453 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 293 Events
- 35 Webinars
- 7.3K Forum Archives