This is day two of an issue that we are experiencing where our live data link to Excel is linking every field except date fields.
Hoping there is a resolution in process for this issue.
How do we submit a ticket for performance issues?
Thanks,
Ken
Thank you, Thank you!! We are back in business. The date fields are now populating properly when using the Live Data Link to Excel.
Have a great day!
Sincerely,
Howdy, I am working on developing a several dashboards for our team, and for whatever reason the widgets I place are multiplying. I have copied/pasted some, but other I have just added I am ending up with dashboards that look like this: When originally I only had the top four items. It has happened on several different…
I am a construction project manager and built sheets that include actual costs for individual tasks, departments and overall project. I update the costs cells as invoices come in by manually calculating then entering in new amount. Ex: Plumbing: week 1 $300, week 2 $250, week 3 $150 = $700. I enter $700 in cell. I'm…
I have multiple items that each have their own statuses and that roll up to "workstreams" or swimlanes. On the dashboard, I would like to show the progress of the items by swimlane without breaking it out into separate widgets for each. This would ideally be a stacked bar where each bar represented the Items and was broken…