I'm trying to delete one task dependency on a Gantt chart. I found this quick YouTube video, which says to click the dependency line, but I'm unable to click on it. My dependency lines are not green like in the YouTube video. Thoughts?
Hello,
That YouTube video appears to be for a different piece of software other than Smartsheet.
If you're trying to delete a dependency in Smartsheet, delete the row reference that you see in the Predecessors column of the Grid portion of the sheet.
More information on dependencies in Smartsheet can be found in this help article: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
How can i create a Report widget that only shows a status with "red status" from my main data source? Do i need to create a separate data source on just my "red status"
Circling back to this….. Another year goes by and still no folder level sharing. Smartsheet developers don't listen to their clients. I have seen hundreds or posts and requests for this over the past 7-8 years. And still NOTHING!! This has been a huge issue for us as a company. As you can tell this is a sore spot for us…
Today a team member accidentally changed several rows by either deleting the data or the row itself. Do I download a snapshot of each one to restore? Some of them didn't seem to be too helpful. What is the protocol for restoring this information? I've only done this before with the help of a representative and it was…