Good Day All:
Is there a way to Auto-fill dates? For example:
04/30/18
05/31/18
06/29/18
Thanks
You could create the first date in the row... then in the 2nd row add this formula in the date column =[date column name]1 + 30
That will calculate your 2nd date, then you can drag down the bottom-right corner to populate the rest of the dates.
Do note that if that first date disappears or changes it will affect the rest of the dates.
Got it, Thanks!
You're welcome! Glad I could assist.
Hey, Is anyone else facing this issue in the approval notifications sent through smartsheet
Hi Smartsheet community, I've always tried to answer questions but this is my first time posting. So I have formula =IF([Project Status]@row = "Complete", 1, 0) set up in the "Complete Check - Hide column" to check the box when the project status is marked complete. The project status column is tied to several other sheets…
I have a sheet with a list of customers in one column, and then the following columns are City, Monday, Tuesday, Wednesday, Thursday, Friday. I need help with a formula that I can put in my sheet summary so that if the customer column says Staples (It can say this in multiple rows) that it will tell me the total package…