How do you structure your formula calculate negative if it is over 100%
For example, I am at 144% which is over budget
Current Formula =AC1 / [Project Budget]1
Results 144%, I would like it to calculate -44% once I am over budget.
Hi Kam,
=IFERROR(IF(AC1 / [Project Budget]1 >1, 1 - AC1 / [Project Budget]1, AC1 / [Project Budget]1),"")
This should do what you're looking for. I threw an IFERROR in there so you didn't get an error result if the values were blank.
Kind regards,
Chris McKay
Thanks!
Hey, Is anyone else facing this issue in the approval notifications sent through smartsheet
Hi Smartsheet community, I've always tried to answer questions but this is my first time posting. So I have formula =IF([Project Status]@row = "Complete", 1, 0) set up in the "Complete Check - Hide column" to check the box when the project status is marked complete. The project status column is tied to several other sheets…
I have a sheet with a list of customers in one column, and then the following columns are City, Monday, Tuesday, Wednesday, Thursday, Friday. I need help with a formula that I can put in my sheet summary so that if the customer column says Staples (It can say this in multiple rows) that it will tell me the total package…