I have an existing sheet which contains a schedule of annually recurring tasks. I saved a copy to create the new year's sheet and now need to update the dates. Is there an automated way to do this?
Hi Cindy,
Yes!
To solve it now I would create a new date column and then put in a rule that takes the original date and adds the number of days to get the new date for this year.
I would also set up the sheet with dependencies to make it even easier to work on in the future
I hope this helps you!
Best,
Andrée Starå - Workflow Consultant / Get Done
You can also do simple Cntrl+F or Cmd+F on a Mac and replace /18 with /19 to update all your date fields fairly quickly. This won't keep the days of the week as accurately as Andree's solution and it might update your days set to 18 to 19, but it would be a fast workaround if your timings are not ultra time sensitive.
I have multiple items that each have their own statuses and that roll up to "workstreams" or swimlanes. On the dashboard, I would like to show the progress of the items by swimlane without breaking it out into separate widgets for each. This would ideally be a stacked bar where each bar represented the Items and was broken…
I have a workspace that I created with two subfolders. A user needs to have access to only one of them but when I have that folder selected, I can only share the entire workspace with them. Is there a secret way that I can share the parent folder and ensure that any new files created will be shared with the same people? I…
I have a Pro plan but I cannot create ANY reports. The system does not allow me to choose a folder, and consequently a sheet to create a row report and suggests an upgrade to Business or Enterprise. I'm quite new to Smartsheet and feel a bit disappointed with this limitation, or maybe I'm just doing something wrong. Alberto