Sign in to join the conversation:
Can anyone tell me what I am doing wrong here? I am trying to automate RYG balls from a % column.
=IF([% Complete]3 < 50, "Red", IF([% Comlete]3 = 100, "Green, IF([% Complete] >50 AND <100, "Yellow")
=IF([% Complete]3 < 50, "Red", IF([% Complete]3 = 100, "Green, IF([% Complete] >50 AND <100, "Yellow")
Corrected spelling error!
Smart sheet displays the percentages as such, but in reality the backend is reading a decimal. When referencing perecentages in formulas you should use .5 for 50% and 1 for 100%. SO your formula would look like this...
=IF([% Complete]3 < .5, "Red", IF([% Complete]3 = 1, "Green, IF([% Complete] >.5 AND <1, "Yellow")
Thanks Mike, but there is still something wrong: unparseable!
I have tried a dozen times with the same results!
Duh I should have looked more carefully! And statements should be made as indicated below...
=IF([% Complete]3 < .5, "Red", IF([% Complete]3 = 1, "Green, IF(AND([% Complete]3 >.5, [% Complete]3 <1), "Yellow")))
You also didn't have enough closing parenthesis.
Maybe I have been staring at this too long! It still doesn't work. Did it work for you?
YOU are a peach, by the way. Thanks for helping.
Are you getting unparseable still?
=IF([% Complete]3 < .5, "Red", IF([% Complete]3 = 1, "Green", IF(AND([% Complete]3 >.5, [% Complete]3 <1), "Yellow")))
Green was missing a closing quotation mark!
Yes
#baldfromtearinghairout
Did this one work?
Green was missing a quotation mark!
I have a sheet that has all of our orders on it. I have other sheets "Gantt" for each machine. I want each machine sheet to auto populate every order that is assigned to it, when an order gets assigned to the machine. I don't want to set an automation to copy the row from the orders sheet to the machine sheet because I…
Hi Community Facing a problem many others have posted about, but haven't seen a solution yet and wondered if it had been solved. I want to be able to add a row on a resource sheet for each project resource once a project has been set to 'X' on a Projects sheet. I have tried through automations but the daisy-chain limit…
Hello! I have this formula that will check the box if the date in a second column is in the past. Is there a way to include if the date is 60 days in the future? Check the box if the date in Column 2 is either (1) in the past or (2) 60 days in the future. IF([GWO - BST (2yr)]@row < TODAY(), 1, 0) Thank you in advance!