Successor needs a Hard start on a Monday following predecessor
Is there a way to set up a SUCCESSOR activity to have a hard start on a given day of the week?
I am in the process of setting up a schedule that requires a SUCCESSOR activity to start on the Monday following its predecessor, regardless of what day of the week that predecessor activity ends on.
Comments
-
=date(year(predecessor@row),month(predecessor@row),day(predecessor@row+1)
-
realized I read that wrong.
=DATE(YEAR(A1), MONTH(A1), DAY(A1) + IF(WEEKDAY(A1) = 1, 1, IF(WEEKDAY(A1) = 3, 6, IF(WEEKDAY(A1) = 4, 5, IF(WEEKDAY(A1) = 5, 4, IF(WEEKDAY(A1) = 6, 3, IF(WEEKDAY(A1) = 7, 2)))))))
-
Thank you Luke. I tried to get it to work but I must be doing something wrong. Because I am relatively new to using Smartsheet, I'm guessing that I must be missing a step when I try to insert the formula. Can you explain how to incorporate it?
-
The best way is to rename your column to A paste the formula in then change your column name back. make sure both columns are the date type
-
I have a similar requirement. The formula works without Dependencies enable but with them enabled, if I try to add a formula to the start, finish or predecessor column nothing works. Is there a way to set a task to start on a following Monday while Dependencies are enabled?
Thanks!
Kate
Categories
- All Categories
- 14 Welcome to the Community
- 10.7K Get Help
- 63 Global Discussions
- 68 Industry Talk
- 385 Announcements
- 3.5K Ideas & Feature Requests
- 55 Brandfolder
- 125 Just for fun
- 50 Community Job Board
- 464 Show & Tell
- 40 Member Spotlight
- 44 Power Your Process
- 28 Sponsor X
- 234 Events
- 7.3K Forum Archives