hello,
i am looking to find a way to do an average with the RYG balls.
ex: 2 green, 2 yellow, 2 red should have should show yellow ball for the overall project.
is this something possible?
thanks for your help
I can't help you with the method, but can I offer some thoughts?
When rolling up status (which isn't a great plan anyway), I always use the worse indicator rather than average.
e.g. if your project has 1 red indicator, it overrides 999 greens or yellows and I'd be reporting the overall status as red because you have an activity which isn't going to make it.
May be better to report on the number of reds, yellows and greens separately?
Not sure what metrics you are using or how you have defined RYG so happy to wind-my-neck-in if necessary!
Hey, Is anyone else facing this issue in the approval notifications sent through smartsheet
Hi Smartsheet community, I've always tried to answer questions but this is my first time posting. So I have formula =IF([Project Status]@row = "Complete", 1, 0) set up in the "Complete Check - Hide column" to check the box when the project status is marked complete. The project status column is tied to several other sheets…
I have a sheet with a list of customers in one column, and then the following columns are City, Monday, Tuesday, Wednesday, Thursday, Friday. I need help with a formula that I can put in my sheet summary so that if the customer column says Staples (It can say this in multiple rows) that it will tell me the total package…