Sign in to join the conversation:
I have groups and sub-groups (I hope I'm using the right terminology, I have 8-rows indented under another row) and only the first four rows are totaling. The calculation is for Duration and I am using days and hours.
Hello bhardin,
Regarding the terminology, I believe the terms you are looking for are Parent Rows and Child Rows. Information about using Hierarchy can be found here:
Regarding the calculation issue, it appears that you've enabled Dependencies, however the calculation only appears to be calculating about two hours rather than eight hours. Have you entered predecessors in your Predecessors column? If predecessors have not been entered, Smartsheet will assume that your tasks are being worked on simultaneously rather than in sequence. Additionally, the Duration shown in the parent row is based off of the Start Date of the first task and the End Date of the last task, not necessarily the sum of the Duration of the child rows.
To resolve your specific issue, in your Predecessors column starting with row 11, try entering the previous row as the predecessor to the current row. More information on this below:
We changed from an enterprise licence to specific accounts. I have a licence and setup a workspace for our global team to edit and collaborate across various sheets. I granted editor can share rights to all non licensed members and shared the publish link with them. This has worked well and allowed them to edit cells,…
This is pulled from a column of responsible person. Why does it display email and not name. How do I correct?
Hi! I have a sheet that has two form that feed into it. This is to report on Closures due to Staffing, Weather, and Facilities. One team submits closures for Staffing and Weather, while another team only submits Facilities. When I created this set up I have it so the one team gets asked "Reason?" then they can select…