I have groups and sub-groups (I hope I'm using the right terminology, I have 8-rows indented under another row) and only the first four rows are totaling. The calculation is for Duration and I am using days and hours.
Hello bhardin,
Regarding the terminology, I believe the terms you are looking for are Parent Rows and Child Rows. Information about using Hierarchy can be found here:
Regarding the calculation issue, it appears that you've enabled Dependencies, however the calculation only appears to be calculating about two hours rather than eight hours. Have you entered predecessors in your Predecessors column? If predecessors have not been entered, Smartsheet will assume that your tasks are being worked on simultaneously rather than in sequence. Additionally, the Duration shown in the parent row is based off of the Start Date of the first task and the End Date of the last task, not necessarily the sum of the Duration of the child rows.
To resolve your specific issue, in your Predecessors column starting with row 11, try entering the previous row as the predecessor to the current row. More information on this below:
I have a form that will be filled out internally. There's a cell labeled "Department" which contains 8 dropdown list values. There's a another cell called "Executives" which are the leaders of these departments. In the form, I'm attempting to do a logic where when you choose a specific "Department", then the cell…
I shared access to a user to a specific folder under workspace A (folder is 2025-09-Service Factory). However, I can see that he's shown to have access to all the other child folders under 02-ACTIVE Initiatives. Why is that when I only shared out one folder? Is there a way to only share access to users to ONLY specific…
what i can do if all my existing smartsheet gant files can't be open after change my plan to Pro? what could be the reason ?